1 BARNES JEWISH HOSPITAL PLZ
| Application date | Oct 14, 2026 |
|---|---|
| Issue date | Oct 19, 2026 |
| Days to issue | 5 |
| Estimated cost | $65,000 |
| Project type | Addition |
| Structure type | 26 |
| First seen | 2026-10-20 11:24:03 |
Description
Boyer Fire shall cut, cap & make safe for the demolition of the existing piping and sprinklers within the existing 3rd floor space. Piping shall be demolished back to the existing 2 1/2" riser located within the chase indicated on FP2. Upon completion of demolition BFP to tie into existing the 2 1/2" riser with a new 4" main that will serve the new 2" branchlines and sprinklers within the new tray storage space. All work to be installed per FM global, NFPA 13, and state/local requirements. All demolition to be performed by others.